فرایند تولید
Commercial Unit
1
- Contract control FM061 including: customer offer price/ installation time/ delivery time/ delivery conditions/ payment terms and, etc. which all is controlled by the sales manager and according to the needs of the customers.
2
- Preparation the material list, which is provided by the planning unit for supply after the contract. Comment: The company has a code in Foolad Mobarakeh & Foolad Oxin Steel Company which can obtain all materials with customer's requested grade along with quality control certificate from Foolad Mobarakeh, Foolad Oxin Company and Iran Mercantile Exchange.
3
- Sending username and password to log in to the customer management system and CCTV
Technical Unit
1
- The possibility of making a metal model with all the details of the actual implementation
- Analysis and design of all steel structures in 3D model
- The possibility of moving in the model and see it at different angles, and the ability to move around like a Resident engineer
- Providing a variety of materials and list offer estimation reports for the executive processes of the parts list
- Possibility of dividing large projects into several sections to separate them into numerous phases
2
- After the workshop maps, WPS are adjusted and announced to the QC unit.
Project Control & Planning Unit
1
- General definition of project process based on Tekla output, importing parts into MSP software and announcing the percentage of progress based on the customer’s expected due date.
2
- Give the cutting order based on PLUS2D output separately, follow it up via QC-FM098 and receive it to continue working.
3
- Micro-processing processes by daily construction planning and control unit according to customers' demands in order of prioritization of construction and installation
Production Unit
1
- 1.Belting 2. Inserting the code of the piece based on Tekla output 3. assembly 4. longitudal welding 5. Accessories 6. Final welding 7. Cleaning 8. Sandblast 9. Color
Quality Control Unit
1
- Each of the above processes is controlled by the QC checklist, sent to the planning unit and enters the product warehouse unit.
2
- Each of these processes is controlled by the QC checklist and returned to the planning unit for the withdrawal of the goods.
3
- Coordination with the employer to send goods with the announcement of the tonnage of the structure
4
- Coordination with the installer and providing the installation map for the installer and the employer. The quality assurance unit of all processes, setting the quality documentation and supervising the procedures for performing the documentation are controlled and supervised by the quality assurance unit.